JV Project between GOS-Engro Group Block II



Block-II: Sindh Engro Coal Mining Company (SECMC)
(GoS 54.7% ; Engro 11.9%; Thal 11.9% ; HUBCO 8.0%; HBL 9.5%; CMEC 4.0%)
Open-pit Coal Mining of 3.8 mtpa upto 7.6 mtpa
2 x 330 MW Power Plants – Operational
1 x 330 Power Plant by Thar energy Ltd – COD achieved
1 x 330 Power Plant by Thal Nova – COD expected by January, 2023

  • June 10, 2018 first coal seam exploited by SECMC at a depth of 140 meters below the surface
  • SECMC declared Phase-I COD on 10th July, 2019
  • Over 14 million Tons of Coal extracted
  • First power unit synchronized with national Grid on 18th March 2019 and supplying 2X330 MW since then
  • More than 13.50 GWH of electricity produced
  • COD Stage Tariff and Financial Close Stage Tariff approved by TCEB for 3.8 Mtpa and 7.6 Mtpa mines respectively
  • COD for Phase-II achieved by SECMC on 30th September, 2022
  • Mine expansion plan up to 12.2 Mtpa is under process by SECMC