Sino-Sindh Resources Block-I



Block-I: Sino Sindh Resources Ltd.(SSRL) .
Open-pit Coal Mining – 7.8 mtpa
2 x 660 MW Power Plants

  • SSRL and Shanghai Electric Group Co. Ltd (SEC) have signed a Coal Supply Agreement for power generation through 2 x 660MW mine mouth power plants
  • Mining lease was granted on 24th May, 2012
  • Feasibility and Contract Stages Tariff approved by the Board in January 2017 and December 2019 respectively
  • Financial Close has achieved on 31st December, 2019 and COD by December, 2022
  • 99% of the over all project completion progress has been achieved
  • First Shovel of Coal was excavated on 31st January 2022
  • 2 X 660 MW Power Plant successfully synchronized with National Grid
    • 1st unit was synchronized on 2nd December, 2022
    • 2nd unit was synchronized on 11th December, 2022
  • 75% : 25% Debt-Equity ratio
  • Wholly foreign funded Project